110444 | Ridge Pike - School Lane to Belvoir Road (CB #0 and TPK Bridge DB-116)/Interchange Area Bridges (Plymouth Township, Montgomery County)
This project is the combined replacement of Montgomery County Bridge #0 and PA Turnpike Bridge DB-116. County Bridge #0 carries Ridge Pike over Norfolk Southern and is 200 feet east of PA Turnpike Bridge DB-116, which carries Ridge Pike over the I-276/Pa Turnpike. Both structures flank the Eastbound On and Eastbound Off Ramps of the future Lafayette Street Interchange, and are in poor condition. This is a companion project to MPMS #48175 and #92839.
Limits: School Lane to Belvoir Road
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | 183 | $800 | $0 | $0 | $0 | $0 |
ROW | LOC | $200 | $0 | $0 | $0 | $0 |
UTL | LOC | $159 | $0 | $0 | $0 | $0 |
UTL | 183 | $637 | $0 | $0 | $0 | $0 |
CON | LOC | $1388 | $296 | $0 | $0 | $0 |
CON | BRIP | $8982 | $0 | $0 | $0 | $0 |
CON | STU | $4243 | $4739 | $0 | $0 | $0 |
CON | TPK | $33677 | $0 | $0 | $0 | $0 |
CON | 183 | $2479 | $889 | $0 | $0 | $0 |
Program Year Totals: | $52,565 | $5,924 | $0 | $0 | ||
Total FY25-FY28 Cost: | $58,489 | Total FY25-FY36 Cost: | $58,489 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
UTL | Plan to Utility Unit | |
FD | 4232 Approved by FHWA | |
ROW | 4232 Approved by FHWA | |
FD | Start of Phase | 2021-12-01 |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2023-03-01 |
FD | PS+E to District Contract Management | 2024-03-07 |
CON | Start of Phase | 2024-05-13 |
CON | Notice to Proceed | 2024-05-13 |
FD | Completion of Phase | 2024-05-13 |
CON | Let | 2025-01-09 |
CON | Award Contract | 2025-02-08 |
CON | Physical Work Complete | 2025-03-31 |
CON | Completion of Phase | 2025-05-30 |
CON | Project Agreement End Date | 2026-09-29 |