110312 | Baltimore Pike/Newark Road Intersection Improvements (New Garden Township, Chester County)
This project is located in the village of Toughkenamon in New Garden Township, Chester County. This project will improve safety by realigning the northern leg of Newark Road at Baltimore Pike and upgrading and modernizing the traffic signal, including pedestrian signals and emergency preemption. Dedicated left-turn lanes on all four approaches, as well as a right-turn lane from northbound Newark Road to eastbound Baltimore Pike will be installed. Turning radii will be widened to accommodate trucks and larger vehicles. Access management enhancements and driveway adjustments for homes and businesses will improve access management. New sidewalk connections and ADA compliant curb ramps will be installed.
Limits: Baltimore Pike at Newark Road
Air Quality Code: R1
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | STU | $1000 | $1000 | $0 | $0 | $0 |
ROW | STU | $0 | $1353 | $0 | $0 | $0 |
UTL | 581 | $0 | $0 | $0 | $0 | $1613 |
CON | 581 | $0 | $0 | $0 | $0 | $9866 |
Program Year Totals: | $1,000 | $2,353 | $0 | $0 | ||
Total FY25-FY28 Cost: | $3,353 | Total FY25-FY36 Cost: | $14,832 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
ROW | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2019-11-01 |
UTL | Start of Phase | 2019-11-01 |
FD | Completion of Phase | 2020-11-30 |
UTL | Completion of Phase | 2020-11-30 |
ROW | Completion of Phase | 2020-11-30 |
CON | Start of Phase | 2021-01-15 |
FD | Start of Phase | 2022-01-04 |
CON | Completion of Phase | 2022-01-30 |
FD | Phase on Approved STIP | |
ROW | Phase on Approved STIP |