110311 | PA 41 at State Road Intersection (Avondale Borough, Chester County)
This project will address the geometry of the intersection, realign the intersection, improve sight distance, improve turning lanes, incorporate ITS, improve sidewalk and pedestrian access, and accommodate heavy vehicle traffic at the intersection.
Limits: PA 41 at State Road
Air Quality Code: R1
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 581 | $563 | $0 | $0 | $0 | $0 |
ROW | STU | $120 | $120 | $0 | $0 | $0 |
UTL | 581 | $0 | $232 | $0 | $0 | $0 |
CON | 581 | $0 | $3650 | $3306 | $0 | $0 |
Program Year Totals: | $683 | $4,002 | $3,306 | $0 | ||
Total FY25-FY28 Cost: | $7,991 | Total FY25-FY36 Cost: | $7,991 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2019-10-02 |
UTL | Start of Phase | 2019-10-02 |
ROW | Completion of Phase | 2020-12-31 |
UTL | Completion of Phase | 2020-12-31 |
FD | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2024-08-15 |
FD | Start of Phase | 2024-10-15 |
FD | PS+E to District Contract Management | 2025-11-15 |
UTL | Plan to Utility Unit | 2025-12-15 |
CON | Let | 2026-03-12 |
CON | Award Contract | 2026-04-11 |
CON | Start of Phase | 2026-05-11 |
CON | Notice to Proceed | 2026-05-11 |
FD | Completion of Phase | 2026-05-13 |
CON | Physical Work Complete | 2028-08-30 |
CON | Completion of Phase | 2028-10-29 |
CON | Project Agreement End Date | 2030-02-28 |