110310 | Almshouse Road at Jacksonville Road Intersection Improvement (Northampton Township, Bucks County)
Provide intersection improvements at Jacksonville Road and Almshouse Road. This may include replacement of the intersection with a roundabout.
Limits: Bucks County
Air Quality Code: 2035M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 581 | $637 | $0 | $0 | $0 | $0 |
ROW | TOLL | $0 | $0 | $0 | $0 | $0 |
ROW | STP | $637 | $0 | $0 | $0 | $0 |
UTL | 581 | $0 | $164 | $0 | $0 | $0 |
CON | STP | $0 | $875 | $875 | $375 | $1375 |
Program Year Totals: | $1,274 | $1,039 | $875 | $375 | ||
Total FY25-FY28 Cost: | $3,563 | Total FY25-FY36 Cost: | $4,938 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Start of Phase | 2021-08-02 |
ROW | Start of Phase | 2021-08-02 |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2023-05-01 |
UTL | Plan to Utility Unit | 2023-05-01 |
CON | Let | 2025-08-01 |
CON | Award Contract | 2025-08-31 |
CON | Notice to Proceed | 2025-09-30 |
CON | Start of Phase | 2025-09-30 |
CON | Physical Work Complete | 2026-11-22 |
CON | Completion of Phase | 2027-01-21 |
CON | Project Agreement End Date | 2028-05-22 |