110309 | I-95/US 13/PA 132 Slip Ramp Operation Improvement (Bristol Township, Bucks County)
As a preliminary step to address congestion and safety issues caused by the antiquated design of the interchange of I-95/US 13/PA 132 (Street Road), the existing intersection will be modified with an operational improvement to provide direct, one-way access to I-95 southbound from the US 13/PA 132 (Street Road) intersection by re-routing traffic from the Street Road off-ramp from eastbound Street Road to I-95 southbound via a direct connection to the I-95 southbound on-ramp. All movements of the interchange are currently provided to access I-95 northbound and southbound, but this reconfigured movement will reduce congestion, improve operational efficiency and system reliability, and eliminate unsafe traffic movements at this heavily trafficked intersection on Street Road at the I-95 southbound entrance.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | 581 | $752 | $0 | $0 | $0 | $0 |
CON | 581 | $0 | $461 | $461 | $250 | $1133 |
CON | STU | $0 | $0 | $1843 | $1000 | $0 |
CON | STP | $0 | $1843 | $0 | $0 | $4529 |
Program Year Totals: | $752 | $2,304 | $2,304 | $1,250 | ||
Total FY25-FY28 Cost: | $6,610 | Total FY25-FY36 Cost: | $12,272 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | Phase Approved by PMC | |
UTL | Start of Phase | 2020-01-02 |
ROW | Start of Phase | 2020-01-02 |
UTL | Completion of Phase | 2021-01-31 |
PE | Start of Phase | 2019-12-30 |
FD | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
PE | Phase on Approved STIP | |
PE | N. E. P. A. Approval | 2023-12-31 |
PE | Completion of Phase | 2024-01-30 |
FD | Start of Phase | 2024-01-30 |
UTL | Plan to Utility Unit | 2024-06-15 |
ROW | Plan to ROW Unit | 2024-07-15 |
ROW | Completion of Phase | 2025-01-02 |
CON | Let | 2026-02-19 |
CON | Award Contract | 2026-03-21 |
FD | Completion of Phase | 2026-04-20 |
CON | Start of Phase | 2026-04-20 |
CON | Notice to Proceed | 2026-04-20 |
CON | Completion of Phase | 2028-04-28 |