110091 | King Road Bridge over Herkaken Creek (New Britain Township, Bucks County)
Bucks County Bridge #54 is a single span, concrete encased, steel I-beam bridge that is approximately 33 feet long. Originally built in 1912, it is currently weight-restricted to 7 tons. The bridge is poor condition as a result of the poor condition of the substructure, due to undermining of the near and far abutments. The bridge railing does not meet current standards and the approach guiderail also requires updating to current standards. Work to be performed includes the complete replacement of the bridge and associated approach improvements.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: King Road Bridge
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | sSTP | $1350 | $0 | $0 | $0 | $0 |
Program Year Totals: | $1,350 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $1,350 | Total FY25-FY36 Cost: | $1,350 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
ROW | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2019-02-01 |
ROW | Completion of Phase | 2020-02-28 |
UTL | Completion of Phase | 2020-02-28 |
ROW | 4232 Approved by FHWA | |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2023-06-01 |
UTL | Start of Phase | 2023-06-01 |
ROW | Plan to ROW Unit | 2023-06-01 |
CON | Start of Phase | 2024-03-11 |
CON | Notice to Proceed | 2024-03-11 |
CON | Let | 2024-09-12 |
CON | Award Contract | 2024-10-12 |
CON | Physical Work Complete | 2025-12-03 |
CON | Completion of Phase | 2026-06-05 |
CON | Project Agreement End Date | 2027-06-03 |