108910 | I-95 Noise Abatement (CNA) (Chester City & Chester Township, Delaware County)
This project is located along I-95 between US 322 and I-476 in the City of Chester and Chester Township, Delaware County and involves the evaluation of potential noise abatement locations. The preliminary phase will include modeling to assess noise reduction benefits to residential areas, and coordination with the municipalities and residents to arrive at a list of priority recommendations for implementation. The selection of locations to receive noise abatement will be based on areas that will realize noise level reductions, benefit the most residents, and can be constructed within funding availability. Preliminary design and environmental evaluations will be completed for the selected locations.
Limits: Highland Avenue to Ridley Creek (I-95 Corridor)
Air Quality Code: X6
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | 581 | $0 | $869 | $0 | $0 | $0 |
UTL | STU | $0 | $0 | $760 | $0 | $0 |
CON | 581 | $0 | $0 | $12167 | $15721 | $172 |
Program Year Totals: | $0 | $869 | $12,927 | $15,721 | ||
Total FY25-FY28 Cost: | $29,517 | Total FY25-FY36 Cost: | $29,689 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
FD | Start of Phase | 2023-08-02 |
ROW | Plan to ROW Unit | 2024-03-01 |
UTL | Plan to Utility Unit | 2024-03-01 |
FD | PS+E to District Contract Management | 2028-09-15 |
CON | Let | 2028-12-14 |
CON | Award Contract | 2029-01-13 |
FD | Completion of Phase | 2029-02-12 |
CON | Start of Phase | 2029-02-12 |
CON | Notice to Proceed | 2029-02-12 |
CON | Physical Work Complete | 2030-06-30 |
CON | Completion of Phase | 2030-08-29 |
CON | Project Agreement End Date | 2031-12-29 |