107945 | Art School Rd O/ Br Pickering Creek (Bridge) (West Pikeland Township, Chester County)
The project involves replacing two bridges along Art School Road (SR 1024) over a branch of Pickering Creek, in West Pikeland Township, Chester County. The proposed work also includes resurfacing the pavement between the two bridges, guide rail, and drainage improvements. The existing structures, both of which were built in 1920, will be replaced on similar horizontal and vertical alignments.
Limits: West Pikeland Township
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | BOF | $995 | $995 | $995 | $0 | $0 |
Program Year Totals: | $995 | $995 | $995 | $0 | ||
Total FY25-FY28 Cost: | $2,985 | Total FY25-FY36 Cost: | $2,985 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Start of Phase | 2018-02-14 |
UTL | Start of Phase | 2018-02-14 |
ROW | Completion of Phase | 2018-12-13 |
UTL | Completion of Phase | 2018-12-13 |
CON | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2023-08-10 |
UTL | Plan to Utility Unit | 2023-08-10 |
CON | Let | 2024-10-10 |
CON | Award Contract | 2024-11-09 |
CON | Start of Phase | 2024-12-09 |
CON | Notice to Proceed | 2024-12-09 |
CON | Physical Work Complete | 2025-10-10 |
CON | Completion of Phase | 2025-12-09 |
CON | Project Agreement End Date | 2027-04-10 |