107642 | Smithbridge Road Corridor (Concord Township, Delaware County)
Construction of 8 ft. multi-use trail along Smithbridge Rd. connecting residential neighborhoods and Garnet Valley School District campuses. Project includes intersection improvements at district campuses. A roundabout will be installed at Smithbridge Rd. and Temple Rd.
Limits: Smithbridge Road in Concord Township
Air Quality Code: 2035M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | CAQ | $1843 | $0 | $0 | $0 | $0 |
CON | HSIP | $1055 | $0 | $0 | $0 | $0 |
Program Year Totals: | $2,898 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $2,898 | Total FY25-FY36 Cost: | $2,898 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
ROW | Start of Phase | 2018-02-14 |
ROW | Phase Approved by PMC | |
ROW | Completion of Phase | 2019-02-28 |
CON | Phase Approved by PMC | |
ROW | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2023-07-15 |
CON | Let | 2023-11-02 |
CON | Award Contract | 2023-12-02 |
CON | Start of Phase | 2024-01-01 |
CON | Notice to Proceed | 2024-01-01 |
CON | Physical Work Complete | 2025-11-05 |
CON | Completion of Phase | 2026-02-28 |
CON | Project Agreement End Date | 2027-05-06 |