107554 | US30 & PA82 Interchange Improvement (West Caln Township & Valley Township, Chester County)
The planned SR 82 Interchange project (US 30, Section 082) is being undertaken in conjunction with corridor wide improvements planned for the 14.5-mile US 30 Coatesville – Downingtown Bypass. The project extends along US 30 from approximately 0.2 miles east of Wagontown Road in Valley Township to 0.1 miles west of the SR 340 bridge over US 30 in Caln Township. Planned work will consist of the full reconstruction of US 30 to upgrade the existing roadway which is approaching the end of its serviceable life. Reconfiguration of the interchange with SR 82 will be undertaken to address substandard acceleration/deceleration ramp lengths and poor geometry of the westbound exit ramp. The project will also address deficient median conditions, shoulder widths and the functionally obsolete bridges (US 30 over W. Brandywine Creek, US 30 over SR 82, & US 30 over Moore Road) within the project limits. Reconfiguration of the SR 82/SR 340 intersection will also be undertaken as part of the project to improve movement through the intersection. No additional travel lanes are proposed on any of the roadways involved in the project.
This is a breakout of MPMS #84884.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 581 | $2521 | $0 | $0 | $0 | $0 |
FD | NHPP | $10085 | $0 | $0 | $0 | $0 |
ROW | 581 | $0 | $0 | $0 | $0 | $3040 |
ROW | NHPP | $0 | $0 | $0 | $0 | $12162 |
UTL | 581 | $0 | $0 | $0 | $0 | $4697 |
CON | 581 | $0 | $0 | $0 | $0 | $65335 |
CON | STP | $0 | $0 | $0 | $0 | $11642 |
CON | SPK-NHPP | $0 | $0 | $0 | $0 | $30000 |
CON | STU | $0 | $0 | $0 | $0 | $95451 |
CON | NHPP | $0 | $0 | $0 | $0 | $44742 |
Program Year Totals: | $12,606 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $12,606 | Total FY25-FY36 Cost: | $279,675 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
ROW | Start of Phase | 2020-09-01 |
UTL | Start of Phase | 2020-09-01 |
FD | Phase on Approved STIP | |
FD | Start of Phase | 2023-10-01 |
UTL | Plan to Utility Unit | 2024-05-15 |
ROW | Plan to ROW Unit | 2024-08-15 |
UTL | Completion of Phase | 2025-09-01 |
ROW | Completion of Phase | 2025-09-01 |
FD | PS+E to District Contract Management | 2026-11-15 |
CON | Let | 2027-12-09 |
CON | Award Contract | 2028-01-08 |
FD | Completion of Phase | 2028-02-07 |
CON | Start of Phase | 2028-02-07 |
CON | Notice to Proceed | 2028-02-07 |
CON | Physical Work Complete | 2029-02-26 |
CON | Completion of Phase | 2029-04-27 |
CON | Project Agreement End Date | 2030-08-27 |