107553 | SR30 & Airport Rd Interchange Improvement (West Caln Township & Valley Township, Chester County)
The planned Airport Road Interchange project (US 30, Section AIR) is being undertaken in conjunction with corridor wide improvements planned for the 14.5-mile US 30 Coatesville – Downingtown Bypass. The project extends along US 30 from approximately 1,500 feet east of the highway’s bridge over Old Mill Road in Sadsbury Township to approximately 0.2 miles east of Wagontown Road in Valley Township. Planned work will consist of the full reconstruction of US 30 to upgrade the existing roadway which is approaching the end of its serviceable life. The Airport Road interchange will be reconfigured to address the short acceleration/deceleration ramp lengths and add the missing westbound entrance and eastbound exit ramps. As part of the interchange reconfiguration turning lanes will be added to Airport Road and West Highland Boulevard will be relocated to align with Highland Boulevard/Airport Road intersection. The project will also address deficient median conditions, shoulder widths and the functionally obsolete bridges (Airport Road over US 30 and US 30 over Wagontown Road) within the project limits. No additional travel lanes are proposed for any of the project roadways
This is a breakout of MPMS #84884
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | TOLL | $0 | $0 | $0 | $0 | $0 |
FD | NHPP | $9000 | $0 | $0 | $0 | $0 |
ROW | 581 | $1494 | $0 | $0 | $0 | $0 |
ROW | NHPP | $5979 | $5979 | $0 | $0 | $0 |
UTL | 581 | $0 | $0 | $1624 | $0 | $0 |
UTL | NHPP | $0 | $0 | $6496 | $0 | $0 |
CON | STP | $0 | $0 | $2477 | $3019 | $44329 |
CON | 581 | $0 | $1494 | $4614 | $5244 | $32562 |
CON | NHPP | $0 | $0 | $5979 | $5979 | $9873 |
CON | STU | $0 | $0 | $0 | $0 | $61923 |
CON | SPK-NHPP | $0 | $0 | $10000 | $15000 | $5000 |
Program Year Totals: | $16,473 | $7,473 | $31,190 | $29,242 | ||
Total FY25-FY28 Cost: | $84,378 | Total FY25-FY36 Cost: | $238,065 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
ROW | Start of Phase | 2020-09-01 |
UTL | Start of Phase | 2020-09-01 |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
FD | Start of Phase | 2023-03-01 |
UTL | Plan to Utility Unit | 2023-05-15 |
ROW | Plan to ROW Unit | 2023-07-15 |
UTL | Completion of Phase | 2025-09-01 |
ROW | Completion of Phase | 2025-09-01 |
FD | PS+E to District Contract Management | 2025-09-15 |
CON | Let | 2026-01-29 |
CON | Award Contract | 2026-03-05 |
CON | Start of Phase | 2026-04-04 |
FD | Completion of Phase | 2026-04-04 |
CON | Notice to Proceed | 2026-04-04 |
CON | Physical Work Complete | 2029-03-03 |
CON | Completion of Phase | 2029-05-02 |
CON | Project Agreement End Date | 2030-09-01 |