107551 | SR30/SR10 to Business 30 Interchange Improvement (Sadsbury Township & West Sadsbury Township, Chester County)
The proposed Octorara Trail (SR 0010)/Lincoln Highway (Business US 30) Interchange project (US 30, Section 010) is being undertaken in conjunction with corridor wide improvements planned for the 14.5-mile US 30 Coatesville – Downingtown Bypass. The project extends along US 30 from approximately 1,250 feet west of SR 10 in West Sadsbury Township to approximately 1,500 feet east of the highway’s bridge over Old Mill Road in Sadsbury Township. Planned work will consist of the full reconstruction of US 30 to upgrade the existing roadway which is approaching the end of its serviceable life. Reconfiguration of the interchange with Business US 30 will be considered to address the existing nonconventional split of the two roadways. The project will also address deficient median conditions, shoulder widths and the functionally obsolete bridges (Business US 30 over EB US 30 and US 30 over Old Mill Road) within the project limits. The addition of turning lanes at the SR 10 intersection will be made to improve movement through the intersection.
This is a breakout of MPMS #84884
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | NHPP | $5222 | $0 | $0 | $0 | $0 |
FD | 581 | $1306 | $0 | $0 | $0 | $0 |
ROW | NHPP | $0 | $6306 | $0 | $0 | $0 |
ROW | 581 | $0 | $1577 | $0 | $0 | $0 |
UTL | 581 | $0 | $0 | $0 | $0 | $532 |
UTL | NHPP | $0 | $0 | $0 | $0 | $2128 |
CON | 581 | $0 | $0 | $0 | $0 | $21375 |
CON | SPK-NHPP | $0 | $0 | $0 | $0 | $40000 |
CON | NHPP | $0 | $0 | $0 | $0 | $45505 |
Program Year Totals: | $6,528 | $7,883 | $0 | $0 | ||
Total FY25-FY28 Cost: | $14,411 | Total FY25-FY36 Cost: | $123,951 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2019-09-01 |
UTL | Start of Phase | 2019-09-01 |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
FD | Start of Phase | 2023-04-01 |
UTL | Plan to Utility Unit | 2023-05-15 |
ROW | Plan to ROW Unit | 2023-07-15 |
UTL | Completion of Phase | 2024-09-01 |
ROW | Completion of Phase | 2024-09-01 |
CON | Award Contract | 2025-10-25 |
FD | Completion of Phase | 2025-11-25 |
CON | Notice to Proceed | 2025-11-25 |
CON | Start of Phase | 2025-11-25 |
FD | PS+E to District Contract Management | 2026-03-15 |
CON | Let | 2026-09-17 |
CON | Completion of Phase | 2028-05-24 |
CON | Physical Work Complete | 2029-06-29 |
CON | Project Agreement End Date | 2030-12-28 |