105803 | PA 309 Connector: Souderton Pike to PA 309 (HT3) (Franconia Township, Hatfield Township & Hilltown Township, Montgomery County)

The PA 309 Connector Project is intended to create an improved connection between PA 63 (near the Lansdale Interchange of I-476) and PA 309 (near the southern terminus of the Sellersville Bypass) in Bucks County. Phase 1, which created a bypass around Mainland village in Montgomery County and reconstructed/widened Wambold Road from PA 63 (Sumneytown Pike) to Allentown Road, was carried under MPMS #16438. Phase 2 is listed under MPMS #77211 and will extend Wambold Rd. on a new alignment and upgrade a portion of Township Line Rd.
Phase 3 will reconstruct and widen Township Line Road between Souderton Pike and the Sellersville Bypass, make a physical connection to PA 309, and is listed under MPMS #105803. Phase 3 will begin along Township Road just east of Hatfield Souderton Road, the terminus of Phase 2. Township Line Road will be widened and the intersection of Bethlehem Pike and Township Line Road will be totally reconstructed to include additional turn lanes. The proposed connector will continue after the intersection to follow existing Fairhill Road and the existing bridge over PA 309 will be reconstructed. The interchange will consist of two ramps, the northbound on ramp intersection will be a proposed roundabout with the proposed connector and existing Fairhill Road. Along Bethlehem Pike improvements will be made to the Bergey Road intersection to the south and Spur Road intersection and County Line Road intersection to the north. The intersection of Bethlehem Pike and County Line will be the location of a proposed roundabout to improve safety and traffic flow.

Limits: Souderton Pike to PA 309
Air Quality Code: 2045M

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FD581$754$0$0$0$0
FDSTU$3016$0$0$0$0
ROW581$750$625$1125$500$0
ROWSTU$3000$2500$4500$2000$0
UTL581$0$348$433$683$0
UTLSTU$0$1390$1730$2730$0
CON581$0$0$413$657$10324
CONSTU$0$0$1652$2626$40558
CONSTP$0$0$0$0$450
Program Year Totals:$7,520$4,863$9,853$9,196 
Total FY25-FY28 Cost:$31,432Total FY25-FY36 Cost:$82,764 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
UTLStart of Phase2015-09-18
ROWStart of Phase2015-09-18
ROWPhase Approved by PMC
UTLPhase Approved by PMC
UTLCompletion of Phase2017-06-14
ROWCompletion of Phase2017-06-14
CONPhase Approved by PMC
UTLPlan to Utility Unit2022-03-01
ROWPhase on Approved STIP
ROWPlan to ROW Unit2023-02-28
CONLet2026-12-10
CONAward Contract2027-01-09
CONStart of Phase2027-02-08
CONNotice to Proceed2027-02-08
CONCompletion of Phase2027-10-04
CONPhysical Work Complete2029-12-29
CONProject Agreement End Date2031-06-29