104343 | US 322 over CSX (Bridge) (Upper Chichester Township & Chester City, Delaware County)
Replacement of the bridge carrying SR 322 over CSX and Bethel Road as well as improvements to the Bethel Road Interchange.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: I-95 Interchange to PA 452 Interchange
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | STU | $3969 | $6798 | $0 | $0 | $0 |
CON | BRIP | $0 | $0 | $4772 | $8144 | $28836 |
Program Year Totals: | $3,969 | $6,798 | $4,772 | $8,144 | ||
Total FY25-FY28 Cost: | $23,683 | Total FY25-FY36 Cost: | $52,519 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Final Utility Clearance | 2022-12-31 |
CON | Award Contract | 2023-05-14 |
CON | Start of Phase | 2023-06-13 |
CON | Notice to Proceed | 2023-06-13 |
CON | Let | 2023-11-02 |
CON | Completion of Phase | 2024-08-31 |
CON | Physical Work Complete | 2027-09-16 |
CON | Project Agreement End Date | 2029-03-16 |