103528 | Mattson Road over the West Branch of the Chester Creek (Chester Heights Borough, Delaware County)
This project is for the bridge rehabilitation or replacement of the County-owned Mattson Road bridge spanning over the West Branch of the Chester Creek in Chester Heights Borough, Delaware County.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
This project is a $5 fee matching funds (sSTP) project.
Limits: Chester Heights Borough
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | TOLL | $0 | $0 | $0 | $0 | $0 |
FD | sSTP | $300 | $0 | $0 | $0 | $0 |
ROW | sSTP | $20 | $0 | $0 | $0 | $0 |
ROW | TOLL | $0 | $0 | $0 | $0 | $0 |
UTL | TOLL | $0 | $0 | $0 | $0 | $0 |
UTL | sSTP | $15 | $0 | $0 | $0 | $0 |
CON | sSTP | $0 | $1315 | $0 | $0 | $0 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
Program Year Totals: | $335 | $1,315 | $0 | $0 | ||
Total FY25-FY28 Cost: | $1,650 | Total FY25-FY36 Cost: | $1,650 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
PE | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2022-06-01 |
UTL | Start of Phase | 2022-06-01 |
PE | Reimbursement Agreement | |
PE | 4232 Approved by FHWA | |
PE | Start of Phase | 2022-08-15 |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
PE | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
ROW | Completion of Phase | 2023-06-01 |
UTL | Completion of Phase | 2023-06-01 |
PE | N. E. P. A. Approval | 2024-12-15 |
PE | Completion of Phase | 2025-01-14 |
FD | Start of Phase | 2025-01-14 |