103440 | Penllyn Pike Bridge Replacement (CB #289) (Whitpain Township, Montgomery County)
The project would involve the rehabilitation or replacement of the bridge that carries Penllyn Pike (Penllyn Blue Bell Pike) over Wissahickon Creek, located in Whitpain Township, Montgomery County. The bridge was constructed in 1964. It is anticipated that the proposed bridge will be replacement on the existing horizontal alignment with minimal approach work to tie back into existing conditions.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Limits: Penllyn Blue Bell Pike O/ Wissahickon Creek
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 185 | $328 | $0 | $0 | $0 | $0 |
ROW | 185 | $82 | $0 | $0 | $0 | $0 |
UTL | 185 | $0 | $0 | $0 | $0 | $61 |
CON | 185 | $0 | $0 | $0 | $0 | $5411 |
Program Year Totals: | $410 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $410 | Total FY25-FY36 Cost: | $5,882 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | Start of Phase | 2023-06-01 |
PE | Completion of Phase | 2023-10-01 |
UTL | Start of Phase | 2023-10-02 |
ROW | Start of Phase | 2023-10-02 |
FD | Completion of Phase | 2024-10-02 |
ROW | Completion of Phase | 2024-10-02 |
UTL | Completion of Phase | 2024-10-02 |
CON | Start of Phase | 2024-11-15 |
FD | Start of Phase | 2025-01-15 |
CON | Completion of Phase | 2027-12-30 |