103372 | Waverly Road over Tacony Creek (County Bridge #275) (Cheltenham Township, Montgomery County)
This project is for the replacement of the bridge that carries Waverly Road over Tacony Creek (County Bridge #275).
Montgomery County Bridge #275 is a 28-foot long single span steel I-beam bridge that carries approximately 2,400 vehicles per day. The bridge is poor condition and the superstructure is in poor condition. The superstructure exhibits significant paint loss with moderate to heavy rust, section loss and pitting. The substructure is exhibiting vertical cracks.
Limits: Waverly Road over Tacony Creek
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | sSTP | $1300 | $0 | $0 | $0 | $0 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
Program Year Totals: | $1,300 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $1,300 | Total FY25-FY36 Cost: | $1,300 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2019-01-07 |
UTL | Start of Phase | 2019-01-07 |
UTL | Completion of Phase | 2019-12-30 |
UTL | 4232 Approved by FHWA | |
ROW | 4232 Approved by FHWA | |
ROW | Completion of Phase | 2019-12-30 |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2023-03-01 |
ROW | Plan to ROW Unit | 2023-03-01 |
CON | Let | 2024-03-14 |
CON | Award Contract | 2024-04-13 |
CON | Start of Phase | 2024-05-13 |
CON | Notice to Proceed | 2024-05-13 |
CON | Physical Work Complete | 2025-06-30 |
CON | Completion of Phase | 2025-08-29 |
CON | Project Agreement End Date | 2026-12-29 |