103371 | Woodmont Road Bridge Replacement (CB #10) (West Conshohocken Borough, Montgomery County)
The project would involve the rehabilitation or replacement of the bridge that carries Woodmont Road over Arrowmink Creek, located in West Conshohocken Borough, Montgomery County. The bridge was constructed in 1932. It is anticipated that the proposed bridge will be replacement on the existing horizontal alignment with minimal approach work to tie back into existing conditions. To maintain access to properties, half width construction will be investigated.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Limits: Woodmont Rd O/Arrowmink Creek, West Conshohocken Boro
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | BRIP | $437 | $0 | $0 | $0 | $0 |
ROW | BRIP | $0 | $225 | $0 | $0 | $0 |
UTL | BRIP | $0 | $124 | $0 | $0 | $0 |
CON | BRIP | $0 | $0 | $0 | $0 | $5534 |
Program Year Totals: | $437 | $349 | $0 | $0 | ||
Total FY25-FY28 Cost: | $786 | Total FY25-FY36 Cost: | $6,320 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | Start of Phase | 2023-05-01 |
UTL | Start of Phase | 2023-10-01 |
PE | Completion of Phase | 2023-10-01 |
ROW | Start of Phase | 2023-10-01 |
ROW | Completion of Phase | 2024-10-01 |
UTL | Completion of Phase | 2024-10-01 |
FD | Completion of Phase | 2024-10-02 |
CON | Start of Phase | 2024-11-15 |
FD | Start of Phase | 2025-01-15 |
CON | Completion of Phase | 2027-12-30 |