102709 | PA 41 & SR 926 Improvements (Londonderry Township, Chester County)
Construction of a roundabout is anticipated at this location. Improvements will provide an opportunity for all users to make safe movements at the four-way PA 41/PA 926 intersection that is currently skewed at approximately 23 degrees, as well as accommodate future traffic demands. Presently, traffic control consists of stop signs on the minor street (PA 926) approaches, with no posted turn restrictions. The approaches of PA 41 consists of one left turn lane and one shared through/right turn lane, while the approaches of PA 926 consists of a single shared left turn/through/right turn lane. After the completion of a needs assessment in 2014, an alternatives analysis identified four alternatives; three of these alternatives (including two alternatives that contain a roundabout) were selected for further evaluation.
PE activities are being completed under MPMS# 14484.
Other PA 41 intersection projects:
PA 41 & Newark Rd - MPMS# 98096
PA 41 & SR 841 - MPMS# 102708
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | STU | $875 | $0 | $0 | $0 | $0 |
Program Year Totals: | $875 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $875 | Total FY25-FY36 Cost: | $875 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
UTL | Plan to Utility Unit | 2021-02-15 |
ROW | 4232 Approved by FHWA | |
ROW | Completion of Phase | |
ROW | Plan to ROW Unit | 2022-02-08 |
UTL | 4232 Approved by FHWA | |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
CON | Let | 2023-08-24 |
CON | Award Contract | 2023-09-23 |
CON | Start of Phase | 2023-10-23 |
CON | Notice to Proceed | 2023-10-23 |
CON | Physical Work Complete | 2025-01-02 |
CON | Completion of Phase | 2025-03-05 |
CON | Project Agreement End Date | 2026-07-03 |