102665 | Signal Upgrade Line Item (Various)
Signal Upgrade Line Item will be used to help address signal retiming hardware and communication related issues that are identified during the installation and implementation of traffic signal retiming (MPMS# 84457) on Critical Corridors in the region.
Limits: Districtwide
Air Quality Code: S7
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | CAQ | $1000 | $1000 | $0 | $0 | $0 |
Program Year Totals: | $1,000 | $1,000 | $0 | $0 | ||
Total FY25-FY28 Cost: | $2,000 | Total FY25-FY36 Cost: | $2,000 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Start of Phase | 2017-10-02 |
CON | Phase on Approved STIP | |