102664 | PA 309 Bridge over Beaver Run (Richland Township, Bucks County)
This project involves rehabilitating or replacing the Bridge at PA309 over Beaver Run. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Limits: Richland Township
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 185 | $170 | $0 | $0 | $0 | $0 |
FD | STP | $679 | $0 | $0 | $0 | $0 |
ROW | STP | $0 | $60 | $0 | $0 | $0 |
ROW | 581 | $0 | $15 | $0 | $0 | $0 |
UTL | 581 | $0 | $0 | $56 | $0 | $0 |
UTL | STP | $0 | $0 | $225 | $0 | $0 |
CON | 185 | $0 | $0 | $1351 | $2444 | $3121 |
Program Year Totals: | $849 | $75 | $1,632 | $2,444 | ||
Total FY25-FY28 Cost: | $5,000 | Total FY25-FY36 Cost: | $8,121 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Start of Phase | |
ROW | Start of Phase | 2022-06-06 |
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
UTL | Completion of Phase | 2023-05-31 |
ROW | Completion of Phase | 2023-05-31 |
PE | N. E. P. A. Approval | 2023-06-30 |
PE | Completion of Phase | 2023-07-30 |
FD | Start of Phase | 2023-07-30 |
UTL | Start of Phase | 2024-01-30 |
UTL | Plan to Utility Unit | 2024-06-30 |
ROW | Plan to ROW Unit | 2024-06-30 |
FD | PS+E to District Contract Management | 2026-06-30 |
CON | Let | 2026-12-10 |
CON | Award Contract | 2027-01-09 |
CON | Start of Phase | 2027-02-08 |
CON | Notice to Proceed | 2027-02-08 |
FD | Completion of Phase | 2027-02-08 |
CON | Physical Work Complete | 2028-12-30 |
CON | Completion of Phase | 2029-02-28 |
CON | Project Agreement End Date | 2030-06-30 |