102309 | PA 309 Bridge over Morgan Creek (Richland Township, Bucks County)
This project involves rehabilitating or replacing the Bridge at PA 309 over Morgan Creek. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Limits: Richland Township
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | STP | $0 | $699 | $0 | $0 | $0 |
FD | 581 | $0 | $175 | $0 | $0 | $0 |
ROW | STP | $0 | $219 | $0 | $0 | $0 |
ROW | 581 | $0 | $55 | $0 | $0 | $0 |
CON | 581 | $0 | $0 | $250 | $338 | $764 |
CON | BRIP | $0 | $0 | $1000 | $1351 | $3053 |
Program Year Totals: | $0 | $1,148 | $1,250 | $1,689 | ||
Total FY25-FY28 Cost: | $4,087 | Total FY25-FY36 Cost: | $7,904 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase on Approved STIP | |
PE | Start of Phase | 2018-10-17 |
ROW | Completion of Phase | 2019-05-31 |
ROW | Start of Phase | 2022-06-06 |
UTL | Start of Phase | 2022-06-06 |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
ROW | Phase Approved by PMC | |
PE | 4232 Approved by FHWA | |
UTL | Completion of Phase | 2023-05-31 |
PE | N. E. P. A. Approval | 2023-06-30 |
PE | Completion of Phase | 2023-07-30 |
FD | Start of Phase | 2023-07-30 |
UTL | Plan to Utility Unit | 2024-06-30 |
ROW | Plan to ROW Unit | 2024-06-30 |
FD | PS+E to District Contract Management | 2025-06-30 |
CON | Let | 2026-12-15 |
CON | Award Contract | 2027-01-14 |
CON | Start of Phase | 2027-02-13 |
CON | Notice to Proceed | 2027-02-13 |
FD | Completion of Phase | 2027-02-13 |
CON | Physical Work Complete | 2029-01-02 |
CON | Completion of Phase | 2029-03-03 |
CON | Project Agreement End Date | 2030-07-03 |