102309 | PA 309 Bridge over Morgan Creek (Richland Township, Bucks County)

This project involves rehabilitating or replacing the Bridge at PA 309 over Morgan Creek. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.

Limits: Richland Township
Air Quality Code: S19

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FDSTP$0$699$0$0$0
FD581$0$175$0$0$0
ROWSTP$0$219$0$0$0
ROW581$0$55$0$0$0
CON581$0$0$250$338$764
CONBRIP$0$0$1000$1351$3053
Program Year Totals:$0$1,148$1,250$1,689 
Total FY25-FY28 Cost:$4,087Total FY25-FY36 Cost:$7,904 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase on Approved STIP
PEStart of Phase2018-10-17
ROWCompletion of Phase2019-05-31
ROWStart of Phase2022-06-06
UTLStart of Phase2022-06-06
UTLPhase Approved by PMC
FDPhase Approved by PMC
PEPhase Approved by PMC
PEPhase on Approved STIP
ROWPhase Approved by PMC
PE4232 Approved by FHWA
UTLCompletion of Phase2023-05-31
PEN. E. P. A. Approval2023-06-30
PECompletion of Phase2023-07-30
FDStart of Phase2023-07-30
UTLPlan to Utility Unit2024-06-30
ROWPlan to ROW Unit2024-06-30
FDPS+E to District Contract Management2025-06-30
CONLet2026-12-15
CONAward Contract2027-01-14
CONStart of Phase2027-02-13
CONNotice to Proceed2027-02-13
FDCompletion of Phase2027-02-13
CONPhysical Work Complete2029-01-02
CONCompletion of Phase2029-03-03
CONProject Agreement End Date2030-07-03