102272 | (Bucks County)

This project will be broken out into two phases when appropriate. Phase I is the replacement/rehabilitation of the poor condition Buck Road Bridge over Mill Creek with a wider structure to accommodate turning lanes and will also include improvements to the Buck Road/Old Bristol Road Intersection. Phase II will consist of improvements including the realignment of the Buck Road/Holland Road intersection and the addition of turning lanes, along with access management and the addition of sidewalks throughout corridor.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or
state Categorical Exclusion clearance.

Limits: Buck Rd from 1,200' south of intersection w/Old Bristol Rd to 1,500' north of intersection w/Holland

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FD185$0$200$0$0$0
CON581$0$1014$676$338$0
CONNHPP$0$4053$2702$1351$0
ROW581$457$0$0$0$0
Program Year Totals:$$$$ 
Total FY25-FY28 Cost:$Total FY25-FY36 Cost:$ 
All costs in thousands.

No milestones are available for this project.