102272 | (Bucks County)
This project will be broken out into two phases when appropriate. Phase I is the replacement/rehabilitation of the poor condition Buck Road Bridge over Mill Creek with a wider structure to accommodate turning lanes and will also include improvements to the Buck Road/Old Bristol Road Intersection. Phase II will consist of improvements including the realignment of the Buck Road/Holland Road intersection and the addition of turning lanes, along with access management and the addition of sidewalks throughout corridor.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or
state Categorical Exclusion clearance.
Limits: Buck Rd from 1,200' south of intersection w/Old Bristol Rd to 1,500' north of intersection w/Holland
| Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
|---|---|---|---|---|---|---|
| FD | 185 | $0 | $200 | $0 | $0 | $0 |
| CON | 581 | $0 | $1014 | $676 | $338 | $0 |
| CON | NHPP | $0 | $4053 | $2702 | $1351 | $0 |
| ROW | 581 | $457 | $0 | $0 | $0 | $0 |
| Program Year Totals: | $ | $ | $ | $ | ||
| Total FY25-FY28 Cost: | $ | Total FY25-FY36 Cost: | $ | |||
| All costs in thousands. | ||||||