102272 | Holland Road at Buck Road and Route 532 (Northampton Township, Bucks County)
This project will be broken out into two phases when appropriate. Phase I is the replacement/rehabilitation of the poor condition Buck Road Bridge over Mill Creek with a wider structure to accommodate turning lanes and will also include improvements to the Buck Road/Old Bristol Road Intersection. Phase II will consist of improvements including the realignment of the Buck Road/Holland Road intersection and the addition of turning lanes, along with access management and the addition of sidewalks throughout corridor.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or
state Categorical Exclusion clearance.
Limits: Buck Rd from 1,200' south of intersection w/Old Bristol Rd to 1,500' north of intersection w/Holland
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | 581 | $457 | $0 | $0 | $0 | $0 |
CON | 581 | $338 | $676 | $676 | $338 | $0 |
CON | NHPP | $1351 | $2702 | $2702 | $1351 | $0 |
Program Year Totals: | $2,146 | $3,378 | $3,378 | $1,689 | ||
Total FY25-FY28 Cost: | $10,591 | Total FY25-FY36 Cost: | $10,591 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
FD | Start of Phase | 2019-10-01 |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
ROW | Start of Phase | 2022-10-31 |
ROW | Plan to ROW Unit | 2023-03-15 |
ROW | Completion of Phase | 2023-10-31 |
FD | PS+E to District Contract Management | 2024-03-14 |
CON | Let | 2024-06-20 |
CON | Award Contract | 2024-07-20 |
CON | Start of Phase | 2024-08-19 |
CON | Notice to Proceed | 2024-08-19 |
FD | Completion of Phase | 2024-08-19 |
CON | Physical Work Complete | 2028-07-03 |
CON | Completion of Phase | 2028-09-01 |
CON | Project Agreement End Date | 2030-01-01 |