❮ Back

T53E | Locomotive Overhaul (Various)

Funding is provided for service reliability to the locomotive fleet based on manufacturer replacement and service standards to maintain equipment through its useful life. In-house staff ensure that each locomotive engine continues to properly function in terms of reliability and fuel consumption, without being remanufactured, specified to work output or miles; and that the locomotive complies with all applicable emission standards.

Limits: Locomotive Overhaul
Air Quality Code: M3

FY2024 TIP for NJ Program Years (in Millions)

PhaseFundFY24FY25FY26FY27LFY28-33
Capital AcquisitionSTATE$0$0$0.147$0.147$0.879
Capital AcquisitionSECT 5337$4.176$2.578$2.578$0$0
Capital AcquisitionSECT 5307$4.176$0$0$0$0
Program Year Totals:$8.352$2.578$2.725$0.147
Total FY24-FY27 Cost:$13.802Total FY24-FY33 Cost:$14.681 
All costs in millions.

No milestones are available for this project.