T50 | Signals and Communications/Electric Traction Systems (Various)
This project provides funding for continued modernization/improvements to the signal and communications systems, including signal/communication upgrade of interlockings, and other communication improvements. This project also provides funding for systemwide electric traction general upgrades including: substation replacement, wayside hot box detection system, rail microwave system upgrades, replacement of substation batteries and electric switch heaters, emergency power backup systemwide, rehabilitation of systemwide overhead catenary structures and foundations including but not limited to acquisition of properties and any items or services needed to support the acquisition. In addition, funding will be provided for Positive Train Control training facilities including but not limited to equipment purchasing, engineering, design, planning, construction, acquisitions and other associated costs.
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Construction | STATE | $2.183 | $1.273 | $0.645 | $0.645 | $3.868 |
Program Year Totals: | $2.183 | $1.273 | $0.645 | $0.645 | ||
Total FY24-FY27 Cost: | $4.746 | Total FY24-FY33 Cost: | $8.614 | |||
All costs in millions. |