T34 | Rail Capital Maintenance (Various)
The Rail Capital Maintenance project includes Rail Maintenance of Way (MOW) activities and Rail Maintenance of Equipment (MOE) activities in accordance with TTF eligibility requirements.
Limits: Rail Capital Maintenance
Air Quality Code: M9
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Capital Acquisition | STATE | $0 | $0 | $4.032 | $5.790 | $34.797 |
Program Year Totals: | $0 | $0 | $4.032 | $5.790 | ||
Total FY24-FY27 Cost: | $9.822 | Total FY24-FY33 Cost: | $44.619 | |||
All costs in millions. |