L064 | Route 206, South Broad Street Bridge over Assunpink Creek (Trenton City, Mercer County)
Initiated by the Bridge Management System, this project will rehabilitate the structurally deficient and functionally obsolete bridge, built in 1843.
Limits: South Broad Street Bridge over Assunpink Creek
Air Quality Code: S19
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Construction | STBGP-TRENTON | $0 | $4.006 | $4.458 | $1.711 | $5.090 |
Program Year Totals: | $0 | $4.006 | $4.458 | $1.711 | ||
Total FY24-FY27 Cost: | $10.175 | Total FY24-FY33 Cost: | $15.265 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Authorize Final Design | 2020-06-15 | 2020-06-19 |
Public Information Center | 2022-03-14 | 2022-03-25 |
Environmental Document Complete | 2022-06-03 | 2022-06-03 |
Authorize Utility Work | 2023-03-17 | 2023-04-28 |
PS&E Certified | 2023-12-07 | 2023-12-07 |
Receive Authorization to Advertise | 2023-12-08 | 2023-12-14 |
Contract Awarded | 2024-02-22 | 2024-02-22 |
Substantial Completion | 2025-05-15 | 2025-05-15 |