This program includes rehabilitation and replacement of interlockings, rail bed, and other rail improvements to ensure overall system safety, reliability, and minimal service disruptions.
Limits: PATCO Interlocking & Track Rehabilitation
| Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
|---|---|---|---|---|---|---|
| Construction | SECT 5307 | $0 | $3.877 | $1.900 | $2.880 | $17.800 |
| Construction | DRPA | $0 | $0.969 | $0.475 | $0.720 | $4.450 |
| Program Year Totals: | ||||||
| Total FY24-FY27 Cost: | Total FY24-FY33 Cost: | |||||
| All costs in millions. | ||||||