355E | Route 295/42/I-76, Direct Connection, Contract 4 (Bellmawr Boro & Mount Ephraim Boro, Camden County)
This project relieves the existing bottleneck at the interchange by constructing; a direct connection on I-295 and other highway improvements, which will reduce congestion and enhance traffic operations and safety throughout the project area. The improvements include; a six lane mainline through the interchange, elimination of dangerous merging and weaving movements, upgrades to ramp geometry and the addition of shoulders throughout the interchange. Contract 4 includes the reconstruction of I-76 and Route 42 along the entire project limits; the completion of new Ramps C & F, and the completion the new I-295 Northbound direct connection. Contract 4 is a breakout of "Route 295/42/I-76, Direct Connection, Camden County".
Limits: Direct Connection, Camden County, Contract 4
Air Quality Code: 2035M
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Construction | NHFP-HWY | $0 | $0 | $0 | $0 | $66.243 |
Construction | NHPP | $0 | $0 | $0 | $0 | $292.707 |
Program Year Totals: | $0 | $0 | $0 | $0 | ||
Total FY24-FY27 Cost: | $0 | Total FY24-FY33 Cost: | $358.950 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Completed Environmental Document | 2009-03-09 | 2009-03-20 |
Authorize Final Design | 2011-08-29 | 2011-09-12 |
ROW Availability | 2013-03-12 | 2014-06-16 |
PS&E Certified | 2024-12-05 | 2024-12-05 |
Receive Authorize to Advertise | 2024-12-06 | 2024-12-12 |
Contract Awarded | 2025-03-04 | 2025-03-04 |
Substantial Completion | 2029-07-30 | 2029-07-30 |