21311 | Route 295 and Route 38 Interchange Operational Improvements (Mount Laurel, Burlington County)
Significant congestion on Route 38 from Duffy's Drive to Route 295 was observed along with insufficient turning movement queues. Improve Mobility, Accessibility, Reliability, Respect Environment Operate Efficiently and increase Safety and Security.
Limits: Route 295 and Route 38 Interchange Operational Improvements
Air Quality Code: 2035M
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Preliminary Engineering | NHPP | $8.000 | $0 | $0 | $0 | $0 |
Design | NHPP | $0 | $0 | $12.000 | $0 | $0 |
Right of Way | NHPP | $0 | $0 | $0 | $0 | $5.000 |
Construction | NHPP | $0 | $0 | $0 | $0 | $242.500 |
Program Year Totals: | $8.000 | $0 | $12.000 | $0 | ||
Total FY24-FY27 Cost: | $20.000 | Total FY24-FY33 Cost: | $267.500 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2021-01-25 | 2021-01-25 |
Develop Community Profile | 2021-03-15 | 2021-04-02 |
Develop Alternatives | 2021-09-13 | 2022-02-11 |
Conduct Proposed Traffic Analysis | 2021-09-13 | 2022-05-10 |
Purpose & Need Statement Completed | 2022-04-29 | 2022-04-29 |
Hold Public Information Center | 2022-09-01 | 2022-10-14 |
Authorize PE Funding | 2023-12-19 | 2024-01-18 |
Concept Development Completed | 2024-03-01 | 2024-03-01 |