18353 | Route 295, Sloan Avenue (CR 649) to CR 583 (Princeton Pike) (Lawrence Twp & Hamilton Twp, Mercer County)
Initiated by the Congestion Management System, this project will address capacity and operational improvements within the project limits.
Limits: Sloan Avenue (CR 649) to CR 583 (Princeton Pike)
Air Quality Code: 2035M
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Preliminary Engineering | CMAQ | $0 | $7.000 | $0 | $0 | $0 |
Design | CMAQ | $0 | $0 | $0 | $8.800 | $0 |
Right of Way | CMAQ | $0 | $0 | $0 | $0 | $15.000 |
Construction | CMAQ | $0 | $0 | $0 | $0 | $127.000 |
Program Year Totals: | $0 | $7.000 | $0 | $8.800 | ||
Total FY24-FY27 Cost: | $15.800 | Total FY24-FY33 Cost: | $157.800 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2018-05-14 | 2018-05-14 |
Purpose & Need Statement Completed | 2019-09-16 | 2019-09-16 |
Develop Alternatives | 2020-09-28 | 2021-03-30 |
Conduct Proposed Traffic Analysis | 2022-04-11 | 2022-07-27 |
Hold Public Information Center | 2023-01-24 | 2023-03-03 |
Authorize PE Funding | 2023-11-03 | 2023-11-13 |
Concept Development Completed | 2023-11-28 | 2023-11-28 |