17419 | Route 1, Alexander Road to Mapleton Road (West Windsor Twp & Plainsboro, Mercer, Middlesex County)
Improvements will help relieve congestion at Route 1 from the “Dinky” railroad bridge to approximately Plainsboro Road by increasing the number of travel lanes from 3 to 4 lanes per direction on Route 1; provide shoulders, deceleration lanes, acceleration lanes, and turn lanes along the corridor for turning vehicles; widen Washington Road at Route 1 to relocate the merge of the 2-lane circle into a single Washington Road lane out of the intersection; increase the Route 1 southbound to Fisher Place jughandle turn; modify existing 3-phase signal at Route 1 and Harrison St. intersection to a 2-phase signal; and provide a Route 1 cross section with 4 lanes per direction at the Millstone River Bridge. This project in West Windsor (Mercer County) and Plainsboro (Middlesex County) is a derivative of the former Rt. 1/CR 571 Penns Neck project (DB #031). The magnitude and scope of work for the Rt. 1 Alexander Rd to Mapleton Rd project is greatly reduced from the Penns Neck project ($150 M vs. $35 M).
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Right of Way | NHPP | $0 | $0 | $5.830 | $0 | $0 |
Construction | NHPP | $0 | $0 | $0 | $0 | $12.095 |
Program Year Totals: | $0 | $0 | $5.830 | $0 | ||
Total FY24-FY27 Cost: | $5.830 | Total FY24-FY33 Cost: | $17.925 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2017-01-20 | 2017-01-20 |
Hold Public Information Center | 2018-08-15 | 2018-08-31 |
Authorize PE Funding | 2019-06-10 | 2019-06-19 |
Concept Development Completed | 2022-05-16 | 2022-05-16 |
Environmental Document Complete | 2022-05-31 | 2022-05-31 |
Hold Public Information Center | 2018-08-15 | 2018-08-31 |
Authorize Final Design | 2023-06-01 | 2023-06-14 |
Authorize ROW | 2024-02-08 | 2024-03-07 |
ROW Availability | 2024-05-01 | 2024-05-01 |
PS&E Certified | 2024-05-01 | 2024-05-01 |
Receive Authorize to Advertise | 2024-05-02 | 2024-05-08 |
Authorize Utility Work | 2024-05-13 | 2024-06-25 |
Contract Awarded | 2024-07-10 | 2024-07-10 |
Substantial Completion | 2025-10-01 | 2025-10-01 |