16342 | Route 73 and Ramp G, Bridge over Route 130 (Pennsauken Twp, Camden County)
Initiated by the Bridge Management System, this project will replace the structurally deficient and functionally obsolete bridge, built in 1930 and modified in 1959.
Limits: Bridge over Rt 130
Air Quality Code: S19
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Design | BFP | $4.674 | $0 | $0 | $0 | $0 |
Right of Way | BFP | $0 | $2.000 | $0 | $0 | $0 |
Construction | NHPP | $0 | $0 | $0 | $0 | $56.200 |
Program Year Totals: | $4.674 | $2.000 | $0 | $0 | ||
Total FY24-FY27 Cost: | $6.674 | Total FY24-FY33 Cost: | $62.874 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2017-01-25 | 2017-01-25 |
Develop Community Profile | 2017-03-30 | 2017-05-02 |
Develop Alternatives | 2017-07-31 | 2017-10-06 |
Conduct Proposed Traffic Analysis | 2017-08-07 | 2017-10-31 |
Purpose & Need Statement Completed | 2017-12-18 | 2017-12-18 |
Hold Public Information Center | 2019-02-25 | 2019-03-11 |
Authorize PE Funding | 2020-04-13 | 2020-05-04 |
Concept Development Completed | 2020-05-15 | 2020-05-15 |
Environmental Document Complete | 2022-09-13 | 2022-09-13 |
Hold Public Information Center | 2019-02-25 | 2019-03-11 |
Authorize Final Design | 2023-04-05 | 2023-04-19 |
Authorize ROW | 2023-10-19 | 2023-11-17 |
Authorize Utility Work | 2023-12-12 | 2024-02-08 |
ROW Availability | 2024-07-23 | 2024-07-23 |
PS&E Certified | 2024-08-06 | 2024-08-06 |
Receive Authorize to Advertise | 2024-08-07 | 2024-08-13 |
Contract Awarded | 2024-11-07 | 2024-11-07 |
Substantial Completion | 2026-02-04 | 2026-02-04 |