16340 | Route 130, Bridge over Main Branch of Newton Creek (Haddon Twp, Camden County)
Initiated by the Bridge Management System, this project will replace the structurally deficient bridge, built in 1927.
Limits: Bridge over Main Branch Newton Creek
Air Quality Code: S19
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Right of Way | BFP | $0 | $1.200 | $0 | $0 | $0 |
Utilities | BFP | $0 | $2.000 | $0 | $0 | $0 |
Construction | NHPP | $0 | $0 | $0 | $0 | $38.450 |
Program Year Totals: | $0 | $3.200 | $0 | $0 | ||
Total FY24-FY27 Cost: | $3.200 | Total FY24-FY33 Cost: | $41.650 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2016-11-21 | 2016-11-21 |
Develop Community Profile | 2017-02-08 | 2017-04-21 |
Develop Alternatives | 2017-09-18 | 2017-09-20 |
Purpose & Need Statement Completed | 2017-10-06 | 2017-10-06 |
Hold Public Information Center | 2018-06-12 | 2018-06-12 |
Authorize PE Funding | 2018-12-11 | 2019-01-07 |
Concept Development Completed | 2020-03-05 | 2020-03-05 |
Hold Public Information Center | 2018-06-12 | 2018-06-12 |
Environmental Document Complete | 2022-06-16 | 2022-06-16 |
Authorize Final Design | 2023-03-06 | 2023-03-17 |
Authorize ROW | 2023-09-18 | 2023-09-29 |
Authorize Utility Work | 2024-02-29 | 2024-04-11 |
ROW Availability | 2024-11-06 | 2024-11-06 |
PS&E Certified | 2024-11-13 | 2024-11-13 |
Receive Authorize to Advertise | 2024-11-14 | 2024-11-20 |
Contract Awarded | 2025-01-28 | 2025-01-28 |
Substantial Completion | 2026-04-22 | 2026-04-22 |