16319 | Route 30, Gibbsboro Road (CR 686) (Clementon Boro & Lindenwold Boro, Camden County)
Initiated from the Safety Management System, the project will improve traffic safety at the intersection as part of the Intersection Improvement Program(IIP). Widening should address the need for dedicated left-turn lanes, and also address the need to improve the level of service by having two through-lanes that will be unencumbered by left-turning vehicles at the intersection
Limits: Gibbsboro Road (CR 686)
Air Quality Code: 2035M
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Design | STBGP-FLEX | $0 | $1.200 | $0 | $0 | $0 |
Right of Way | STBGP-FLEX | $0 | $2.300 | $0 | $0 | $0 |
Construction | STBGP-FLEX | $0 | $0 | $0 | $0 | $6.450 |
Program Year Totals: | $0 | $3.500 | $0 | $0 | ||
Total FY24-FY27 Cost: | $3.500 | Total FY24-FY33 Cost: | $9.950 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2016-04-05 | 2016-04-05 |
Develop Community Profile | 2017-10-13 | 2017-10-19 |
Develop Alternatives | 2017-11-13 | 2017-12-11 |
Purpose & Need Statement Completed | 2018-04-30 | 2018-04-30 |
Conduct Proposed Traffic Analysis | 2018-05-01 | 2018-05-21 |
Hold Public Information Center | 2018-11-23 | 2018-12-10 |
Concept Development Completed | 2019-05-22 | 2019-05-22 |
Authorize PE Funding | 2021-06-01 | 2021-06-14 |
Environmental Document Complete | 2022-10-18 | 2022-10-18 |
Hold Public Information Center | 2018-11-23 | 2018-12-10 |
Authorize Final Design | 2023-10-26 | 2023-11-01 |
Authorize ROW | 2024-06-27 | 2024-07-25 |
Authorize Utility Work | 2024-09-30 | 2024-11-13 |
ROW Availability | 2025-08-21 | 2025-08-21 |
PS&E Certified | 2025-10-27 | 2025-10-27 |
Receive Authorize to Advertise | 2025-10-28 | 2025-11-03 |
Contract Awarded | 2026-01-07 | 2026-01-07 |
Substantial Completion | 2027-03-18 | 2027-03-18 |