15385 | Route 38, Nixon Drive to Route 295 Bridge (Moorestown Twp, Mount Laurel Twp, Lumberton Twp & Mount Holly Twp, Burlington County)
This project will mill/pave the shoulder area and include treatment on the existing mainline pavement within the project limits. Sidewalk improvements, ADA compliance, traffic signal upgrades and guide rail upgrades will be included as well.
Limits: Nixon Drive to Route 295
Air Quality Code: S10
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Construction | BFP | $0 | $8.130 | $0 | $0 | $0 |
Program Year Totals: | $0 | $8.130 | $0 | $0 | ||
Total FY24-FY27 Cost: | $8.130 | Total FY24-FY33 Cost: | $8.130 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Develop Alternatives | 2017-10-18 | 2017-10-24 |
Concept Development Initiated | 2018-06-18 | 2018-06-18 |
Purpose & Need Statement Completed | 2018-12-07 | 2018-12-07 |
Concept Development Complete | 2019-08-14 | 2019-08-14 |
Environmental Document Complete | 2019-09-19 | 2019-09-19 |
Authorize Final Design | 2019-12-03 | 2019-12-09 |
Authorize ROW | 2022-07-12 | 2022-08-08 |
ROW Availability | 2023-06-16 | 2023-06-16 |
PS&E Certified | 2023-07-18 | 2023-07-18 |
Receive Authorize to Advertise | 2023-07-19 | 2023-07-25 |
Contract Awarded | 2023-09-21 | 2023-09-21 |
Substantial Completion | 2024-05-02 | 2024-05-02 |