15375 | Route 30, Cooper Street to Grove Street (Camden City, Collingswood Boro, Audubon Boro & Haddon Heights Boro, Camden County)
Initiated from the Pavement Management System, this project will resurface the pavement within the project limits.
Limits: Cooper St to Grove St
Air Quality Code: S10
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Construction | NHPP | $0 | $46.500 | $0 | $0 | $0 |
Program Year Totals: | $0 | $46.500 | $0 | $0 | ||
Total FY24-FY27 Cost: | $46.500 | Total FY24-FY33 Cost: | $46.500 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2016-12-09 | 2016-12-09 |
Develop Alternatives | 2017-07-06 | 2017-10-16 |
Purpose & Need Statement Completed | 2017-08-01 | 2017-08-01 |
Environmental Document Complete | 2019-09-20 | 2019-09-20 |
Authorize Final Design | 2020-03-30 | 2020-04-03 |
Concept Development Complete | 2022-04-18 | 2022-04-18 |
Authorize Utility Work | 2022-05-09 | 2022-05-20 |
Authorize ROW | 2022-06-29 | 2022-07-27 |
ROW Availability | 2023-10-03 | 2023-10-03 |
PS&E Certified | 2023-10-18 | 2023-10-18 |
Receive Authorize to Advertise | 2023-10-19 | 2023-10-25 |
Contract Awarded | 2024-01-18 | 2024-01-18 |
Substantial Completion | 2024-08-23 | 2024-08-23 |