15321 | (Burlington County)
Initiated by the Bridge Management System, this project will replace the bridge, built in 1931.
Limits: Bridge over Mount Misery Brook
| Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
|---|---|---|---|---|---|---|
| Construction | NHPP | $0 | $0 | $0 | $0 | $13.700 |
| Program Year Totals: | ||||||
| Total FY24-FY27 Cost: | Total FY24-FY33 Cost: | |||||
| All costs in millions. | ||||||