15317 | Route 64, Bridge over Amtrak (West Windsor Twp, Mercer County)
Initiated by the Bridge Management System, this project will replace the structurally deficient bridge.
Limits: Bridge over Amtrak
Air Quality Code: S19
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Design | NHPP | $0 | $0 | $4.200 | $0 | $0 |
Right of Way | NHPP | $0 | $0 | $0 | $3.000 | $0 |
Construction | NHPP | $0 | $0 | $0 | $0 | $31.300 |
Program Year Totals: | $0 | $0 | $4.200 | $3.000 | ||
Total FY24-FY27 Cost: | $7.200 | Total FY24-FY33 Cost: | $38.500 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2019-04-15 | 2019-04-15 |
Develop Community Profile | 2019-07-18 | 2019-08-07 |
Conduct Proposed Traffic Analysis | 2019-11-04 | 2019-11-15 |
Develop Alternatives | 2020-04-01 | 2021-06-07 |
Purpose & Need Statement Completed | 2020-04-10 | 2020-04-10 |
Hold Public Information Center | 2022-03-15 | 2022-04-26 |
Authorize PE Funding | 2023-04-10 | 2023-04-14 |
Concept Development Completed | 2023-05-26 | 2023-05-26 |