15301 | (Mercer County)
Initiated from the Drainage Management System, this study will explore drainage improvements within the project limits.
Limits: Hill Top Drive
| Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
|---|---|---|---|---|---|---|
| Right of Way | NHPP | $0 | $0 | $0 | $1.000 | $0 |
| Construction | NHPP | $0 | $0 | $0 | $0 | $1.950 |
| Design | NHPP | $0 | $0 | $1.400 | $0 | $0 |
| Preliminary Engineering | NHPP | $0 | $1.000 | $0 | $0 | $0 |
| Program Year Totals: | ||||||
| Total FY24-FY27 Cost: | Total FY24-FY33 Cost: | |||||
| All costs in millions. | ||||||