14426 | Route 130, Bridge over Big Timber Creek (Camden County)

Initiated by the Bridge Management System, this project will replace the structurally deficient and functionally obsolete bridge, built in 1928. Improvements will also be made to the approaches, and to the drainage at the site.

Limits: Bridge over Big Timber Creek
Air Quality Code: S19

FY2024 TIP for NJ Program Years (in Millions)

PhaseFundFY24FY25FY26FY27LFY28-33
ConstructionNHPP$0.222$0$0$0$0
Program Year Totals:$0.222$0$0$0
Total FY24-FY27 Cost:$0.222Total FY24-FY33 Cost:$0.222 
All costs in millions.

Milestones

PhaseMilestoneEstimated Date
Concept Development Initiated2014-07-142014-07-14
Develop Community Profile2014-11-052014-12-15
Purpose & Need Statement Completed2015-04-242015-04-24
Develop Alternatives2015-04-242015-05-22
Hold Public Information Center2015-06-152015-07-16
Authorize PE Funding2016-10-162017-03-14
Concept Development Complete2017-04-192017-04-19
Hold Public Information Center2015-06-152015-07-16
Authorize FD2019-05-172019-05-31
Environmental Document Complete2019-05-282019-05-28
Authorize ROW2020-04-012020-04-03
ROW Availability2022-04-082022-04-08
Authorize Utility Work2022-04-292022-05-05
PS&E Certified2022-05-122022-05-12
Receive Authorization to Advertise2022-05-132022-05-19
Contract Awarded2022-06-302022-06-30
Substantial Completion2024-08-202024-08-20