14426 | Route 130, Bridge over Big Timber Creek (Camden County)
Initiated by the Bridge Management System, this project will replace the structurally deficient and functionally obsolete bridge, built in 1928. Improvements will also be made to the approaches, and to the drainage at the site.
Limits: Bridge over Big Timber Creek
Air Quality Code: S19
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Construction | NHPP | $0.222 | $0 | $0 | $0 | $0 |
Program Year Totals: | $0.222 | $0 | $0 | $0 | ||
Total FY24-FY27 Cost: | $0.222 | Total FY24-FY33 Cost: | $0.222 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2014-07-14 | 2014-07-14 |
Develop Community Profile | 2014-11-05 | 2014-12-15 |
Purpose & Need Statement Completed | 2015-04-24 | 2015-04-24 |
Develop Alternatives | 2015-04-24 | 2015-05-22 |
Hold Public Information Center | 2015-06-15 | 2015-07-16 |
Authorize PE Funding | 2016-10-16 | 2017-03-14 |
Concept Development Complete | 2017-04-19 | 2017-04-19 |
Hold Public Information Center | 2015-06-15 | 2015-07-16 |
Authorize FD | 2019-05-17 | 2019-05-31 |
Environmental Document Complete | 2019-05-28 | 2019-05-28 |
Authorize ROW | 2020-04-01 | 2020-04-03 |
ROW Availability | 2022-04-08 | 2022-04-08 |
Authorize Utility Work | 2022-04-29 | 2022-05-05 |
PS&E Certified | 2022-05-12 | 2022-05-12 |
Receive Authorization to Advertise | 2022-05-13 | 2022-05-19 |
Contract Awarded | 2022-06-30 | 2022-06-30 |
Substantial Completion | 2024-08-20 | 2024-08-20 |