This project will improve operational and safety conditions within the Route 73 corridor. A focus will be placed on improvements at the intersections of Route 73 and Church Road and Route 73 and Fellowship Road. This project will also include a pedestrian overpass, utility relocations, ROW acquisitions, ramp relocations, and road way realignment.
Limits: Church Road (CR 616) and Fellowship Road (CR 673) Intersections
Air Quality Code: 2035M
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Right of Way | NHPP | $0 | $20.000 | $0 | $0 | $0 |
Construction | NHPP | $0 | $0 | $0 | $0 | $128.500 |
Program Year Totals: | $0 | $20.000 | $0 | $0 | ||
Total FY24-FY27 Cost: | $20.000 | Total FY24-FY33 Cost: | $148.500 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2013-07-01 | 2013-07-01 |
Develop Community Profile | 2014-06-16 | 2014-07-14 |
Complete Purpose & Need Statement | 2014-11-12 | 2014-11-12 |
Develop Alternatives | 2014-11-13 | 2015-04-17 |
Conduct Proposed Traffic Analysis | 2015-01-15 | 2015-04-17 |
Hold Public Information Center | 2016-01-18 | 2016-03-23 |
Authorize PE Funding | 2018-08-01 | 2018-08-21 |
Concept Development Complete | 2019-01-04 | 2019-01-04 |
Hold Public Information Center | 2016-01-18 | 2016-03-23 |
Environmental Document Complete | 2022-07-01 | 2022-07-01 |
Authorize Final Design | 2022-09-21 | 2022-09-22 |
Authorize ROW | 2023-04-20 | 2023-05-17 |
Authorize Utility Work | 2023-08-08 | 2023-09-19 |
ROW Availability | 2025-04-09 | 2025-04-09 |
PS&E Certified | 2025-05-08 | 2025-05-08 |
Receive Authorize to Advertise | 2025-05-16 | 2025-05-29 |
Contract Awarded | 2025-09-04 | 2025-09-04 |
Substantial Completion | 2026-12-01 | 2026-12-01 |