12380 | Route 73, Church Road (CR 616) and Fellowship Road (CR 673) Intersections (Mount Laurel Twp, Burlington County)

This project will improve operational and safety conditions within the Route 73 corridor. A focus will be placed on improvements at the intersections of Route 73 and Church Road and Route 73 and Fellowship Road. This project will also include a pedestrian overpass, utility relocations, ROW acquisitions, ramp relocations, and road way realignment.

Limits: Church Road (CR 616) and Fellowship Road (CR 673) Intersections
Air Quality Code: 2035M

FY2024 TIP for NJ Program Years (in Millions)

PhaseFundFY24FY25FY26FY27LFY28-33
Right of WayNHPP$0$20.000$0$0$0
ConstructionNHPP$0$0$0$0$128.500
Program Year Totals:$0$20.000$0$0
Total FY24-FY27 Cost:$20.000Total FY24-FY33 Cost:$148.500 
All costs in millions.

Milestones

PhaseMilestoneEstimated Date
Concept Development Initiated2013-07-012013-07-01
Develop Community Profile2014-06-162014-07-14
Complete Purpose & Need Statement2014-11-122014-11-12
Develop Alternatives2014-11-132015-04-17
Conduct Proposed Traffic Analysis2015-01-152015-04-17
Hold Public Information Center2016-01-182016-03-23
Authorize PE Funding2018-08-012018-08-21
Concept Development Complete2019-01-042019-01-04
Hold Public Information Center2016-01-182016-03-23
Environmental Document Complete2022-07-012022-07-01
Authorize Final Design2022-09-212022-09-22
Authorize ROW2023-04-202023-05-17
Authorize Utility Work2023-08-082023-09-19
ROW Availability2025-04-092025-04-09
PS&E Certified2025-05-082025-05-08
Receive Authorize to Advertise2025-05-162025-05-29
Contract Awarded2025-09-042025-09-04
Substantial Completion2026-12-012026-12-01