12346A | Route 130, CR 545 (Farnsworth Avenue) (Bordentown Twp, Burlington County)
Initiated from the Office of Bicycle and Pedestrian Programs, this project, a breakout from "Route 130/206, CR 528 (Crosswicks Rd) to Route 206 at Amboy Rd", will address pedestrian and bicycle deficiencies within the project limits.
Limits: Intersection at Farnsworth Avenue
Air Quality Code: A2
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Construction | NHPP | $0 | $11.100 | $0 | $0 | $0 |
Program Year Totals: | $0 | $11.100 | $0 | $0 | ||
Total FY24-FY27 Cost: | $11.100 | Total FY24-FY33 Cost: | $11.100 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2013-09-16 | 2013-09-16 |
Develop Community Profile | 2013-10-22 | 2013-12-31 |
Develop Alternatives | 2014-06-23 | 2014-07-14 |
Purpose & Need Statement Completed | 2014-07-18 | 2014-07-18 |
Conduct Proposed Traffic Analysis | 2014-07-21 | 2014-08-01 |
Hold Public Information Center | 2014-09-26 | 2014-12-15 |
Authorize PE Funding | 2016-08-25 | 2016-09-12 |
Concept Development Complete | 2017-01-17 | 2017-01-17 |
Authorize FD | 2019-09-18 | 2019-10-07 |
Environmental Document Complete | 2022-11-15 | 2022-11-15 |
Authorize ROW | 2023-04-20 | 2023-04-26 |
Authorize Utility Work | 2023-05-04 | 2023-06-15 |
ROW Availability | 2023-09-11 | 2023-09-11 |
PS&E Certified | 2023-10-10 | 2023-10-10 |
Receive Authorization to Advertise | 2023-10-11 | 2023-10-31 |
Contract Awarded | 2024-01-12 | 2024-01-12 |
Substantial Completion | 2025-03-24 | 2025-03-24 |