12346 | Route 130/206, CR 528 (Crosswicks Rd) to Rt 206 at Amboy Rd (Bordentown Twp & Bordentown City, Burlington County)
Initiated from the Office of Bicycle and Pedestrian Programs, this project will address pedestrian and bicycle deficiencies within the project limits.
Limits: Bicycle and Pedestrian Plan
Air Quality Code: A2
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Right of Way | NHPP | $0 | $0.500 | $0 | $0 | $0 |
Construction | NHPP | $0 | $0 | $0 | $0 | $6.250 |
Program Year Totals: | $0 | $0.500 | $0 | $0 | ||
Total FY24-FY27 Cost: | $0.500 | Total FY24-FY33 Cost: | $6.750 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Develop Community Profile | 2013-11-01 | 2013-12-31 |
Concept Development Initiated | 2013-12-16 | 2013-12-16 |
Develop Alternatives | 2014-06-20 | 2014-06-27 |
Conduct Proposed Traffic Analysis | 2014-06-30 | 2014-07-14 |
Purpose & Need Statement Completed | 2014-07-17 | 2014-07-17 |
Hold Public Information Center | 2014-09-15 | 2014-12-15 |
Authorize PE Funding | 2018-12-13 | 2019-01-11 |
Concept Development Complete | 2019-02-26 | 2019-02-26 |
Environmental Document Complete | 2022-06-17 | 2022-06-17 |
Authorize Final Design | 2022-07-27 | 2022-08-02 |
Authorize ROW | 2023-02-28 | 2023-05-09 |
Authorize Utility Work | 2023-05-17 | 2023-06-29 |
ROW Availability | 2024-01-05 | 2024-01-05 |
PS&E Certified | 2024-01-05 | 2024-01-05 |
Receive Authorization to Advertise | 2024-01-08 | 2024-01-12 |
Contract Awarded | 2024-03-18 | 2024-03-18 |
Substantial Completion | 2025-06-10 | 2025-06-10 |