12307 | Route 38, South Church Street (CR 607) to Fellowship Road (CR 673), Operational and Safety Improvements (Moorestown Twp, Burlington County)
The purpose of this project is to reconfigure the Route 38 and South Church Street/Fellowship Rd. intersection layout, improve congestion, improve safety, and ensure ADA compliance throughout the intersection. In addition the existing S. Church St. Bridge will be replaced and widened, deficiencies in sidewalk, curbs and curb ramps will be addressed. The existing shoulders and auxiliary lanes will be brought into compliance with NJDOT standards.
Air Quality Code: 2035M
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Right of Way | NHPP | $9.525 | $0 | $0 | $0 | $0 |
Construction | NHPP | $0 | $0 | $0 | $26.250 | $0 |
Program Year Totals: | $9.525 | $0 | $0 | $26.250 | ||
Total FY24-FY27 Cost: | $35.775 | Total FY24-FY33 Cost: | $35.775 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2012-11-19 | 2012-11-19 |
Develop Alternatives | 2013-04-29 | 2013-05-06 |
Conduct Proposed Traffic Analysis | 2013-05-07 | 2013-06-14 |
Hold Public Information Center | 2013-09-02 | 2013-09-24 |
Authorize PE Funding | 2016-06-09 | 2016-06-09 |
Concept Development Complete | 2016-08-03 | 2016-08-03 |
Authorize FD | 2018-06-06 | 2018-06-11 |
Environmental Document Complete | 2022-02-01 | 2022-02-01 |
Authorize ROW | 2022-10-31 | 2022-11-30 |
Authorize Utility Work | 2023-03-08 | 2023-04-19 |
ROW Availability | 2024-03-22 | 2024-03-22 |
PS&E Certified | 2024-04-08 | 2024-04-08 |
Receive Authorization to Advertise | 2024-04-16 | 2024-05-06 |
Contract Awarded | 2024-07-10 | 2024-07-10 |
Substantial Completion | 2025-10-01 | 2025-10-01 |