12307 | Route 38, South Church Street (CR 607) to Fellowship Road (CR 673), Operational and Safety Improvements (Moorestown Twp, Burlington County)

The purpose of this project is to reconfigure the Route 38 and South Church Street/Fellowship Rd. intersection layout, improve congestion, improve safety, and ensure ADA compliance throughout the intersection. In addition the existing S. Church St. Bridge will be replaced and widened, deficiencies in sidewalk, curbs and curb ramps will be addressed. The existing shoulders and auxiliary lanes will be brought into compliance with NJDOT standards.

Air Quality Code: 2035M

FY2024 TIP for NJ Program Years (in Millions)

PhaseFundFY24FY25FY26FY27LFY28-33
Right of WayNHPP$9.525$0$0$0$0
ConstructionNHPP$0$0$0$26.250$0
Program Year Totals:$9.525$0$0$26.250
Total FY24-FY27 Cost:$35.775Total FY24-FY33 Cost:$35.775 
All costs in millions.

Milestones

PhaseMilestoneEstimated Date
Concept Development Initiated2012-11-192012-11-19
Develop Alternatives2013-04-292013-05-06
Conduct Proposed Traffic Analysis2013-05-072013-06-14
Hold Public Information Center2013-09-022013-09-24
Authorize PE Funding2016-06-092016-06-09
Concept Development Complete2016-08-032016-08-03
Authorize FD2018-06-062018-06-11
Environmental Document Complete2022-02-012022-02-01
Authorize ROW2022-10-312022-11-30
Authorize Utility Work2023-03-082023-04-19
ROW Availability2024-03-222024-03-22
PS&E Certified2024-04-082024-04-08
Receive Authorization to Advertise2024-04-162024-05-06
Contract Awarded2024-07-102024-07-10
Substantial Completion2025-10-012025-10-01