12306 | Route 42, Kennedy Ave. to Atlantic City Expressway (Gloucester County)
Initiated from the Pavement Management System, this project will resurface, rehabilitate and reconstruct within the project limits. ADA compliance improvements will be included.
Air Quality Code: S10
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Construction | NHPP | $14.500 | $0 | $0 | $0 | $0 |
Program Year Totals: | $14.500 | $0 | $0 | $0 | ||
Total FY24-FY27 Cost: | $14.500 | Total FY24-FY33 Cost: | $14.500 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2012-05-07 | 2012-05-07 |
Develop Alternatives | 2013-01-15 | 2013-03-20 |
Complete Purpose & Need Statement | 2013-02-28 | 2013-02-28 |
Conduct Proposed Traffic Analysis | 2013-03-12 | 2014-01-17 |
Hold Public Information Center | 2013-05-02 | 2013-08-12 |
Concept Development Complete | 2014-01-17 | 2014-01-17 |
Authorize PE Funding | 2014-06-14 | 2014-06-24 |
Hold Public Information Center | 2013-05-02 | 2013-08-12 |
Environmental Document Complete | 2017-08-17 | 2017-08-17 |
Authorize ROW | 2017-10-16 | 2017-10-31 |
Authorize FD | 2018-05-21 | 2018-05-29 |
ROW Availability | 2022-09-07 | 2022-09-07 |
Authorize Utility Work | 2022-09-09 | 2022-11-04 |
PS&E Certified | 2023-05-11 | 2023-05-11 |
Receive Authorization to Advertise | 2023-05-12 | 2023-05-25 |
Contract Awarded | 2023-07-31 | 2023-07-31 |
Substantial Completion | 2024-10-22 | 2024-10-22 |