12305 | Route 47, Grove St. to Route 130, Pavement (Glassboro Boro, Westville Boro & Deptford Twp, Gloucester County)
Initiated from the Pavement Management System, this project will resurface, rehabilitate and reconstruct within the project limits. The project will update the ADA requirements, and correct a culvert which causes a flooding condition.
Air Quality Code: S10
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Construction | STBGP-FLEX | $89.700 | $0 | $0 | $0 | $0 |
Program Year Totals: | $89.700 | $0 | $0 | $0 | ||
Total FY24-FY27 Cost: | $89.700 | Total FY24-FY33 Cost: | $89.700 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2012-07-09 | 2012-07-09 |
Develop Alternatives | 2013-05-13 | 2013-07-16 |
Conduct Proposed Traffic Analysis | 2013-05-13 | 2013-07-16 |
Complete Purpose & Need Statement | 2013-05-15 | 2013-05-15 |
Hold Public Information Center | 2013-08-01 | 2013-10-24 |
Authorize PE Funding | 2014-11-06 | 2015-05-08 |
Concept Development Complete | 2015-06-30 | 2015-06-30 |
Hold Public Information Center | 2013-08-01 | 2013-10-24 |
Authorize FD | 2018-05-22 | 2018-05-24 |
Environmental Document Complete | 2018-12-10 | 2018-12-10 |
Authorize ROW | 2019-06-10 | 2019-06-24 |
Authorize Utility Work | 2022-07-14 | 2022-08-24 |
ROW Availability | 2023-07-05 | 2023-07-05 |
Receive Authorization to Advertise | 2023-07-24 | 2023-08-04 |
PS&E Certified | 2023-08-10 | 2023-08-10 |
Contract Awarded | 2023-10-26 | 2023-10-26 |
Substantial Completion | 2025-01-23 | 2025-01-23 |