11326C | Route 76/676 Bridges and Pavement, Contract 3 (Camden City & Gloucester City, Camden County)
The project will replace: the bridge decks and superstructure of Route 76/676 over the Main Branch of Newton Creek, and Route 76 over Nicholson Road; the deck and superstructure of Route 76 over the South Branch of Newton Creek, Conrail, & Klemm Avenue; and the deck and superstructure of Route 676 Southbound over the Main Branch of Newton Creek. Some pavement resurfacing of Route 676 to the bridge decks at North Branch of Newton Creek and on Route 76 Southbound will be included. Two bridges; Route 676 Southbound over Main Branch of Newton Creek, and Route 76 over Main Branch of Newton Creek, will be widened. Resurfacing at; Morgan Boulevard Eastbound to the Route 676 Northbound loop ramp, Collings Avenue to Route 676 Northbound, Route 676 Southbound to Collings Avenue Westbound, Route 676 Southbound to Collings Avenue Eastbound, Collings Avenue to Route 676 Southbound, and Route 676 Southbound to Route 76C Eastbound will also be performed.The projects also includes; ADA improvements at the Morgan Boulevard and Route 676 ramp; intersection and traffic signal modifications at the Collings Avenue and Route 676 Northbound ramp intersection, and the Collings Avenue and Route 676 Southbound ramp intersection.
Limits: Bridge Deck Replacements
Air Quality Code: S19
FY2024 TIP for NJ Program Years (in Millions)
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|
Construction | NHPP | $92.800 | $0 | $0 | $0 | $0 |
Program Year Totals: | $92.800 | $0 | $0 | $0 |
Total FY24-FY27 Cost: | $92.800 | Total FY24-FY33 Cost: | $92.800 | |
All costs in millions. |
Milestones
Phase | Milestone | Estimated Date |
---|
Environmental Document Completed | 2019-05-27 | 2019-06-03 |
Authorize Utility Work | 2023-05-04 | 2023-06-15 |
PS&E Certified | 2023-11-24 | 2023-11-24 |
Receive Authorize to Advertise | 2023-11-27 | 2023-12-01 |
Contract Awarded | 2024-02-12 | 2024-02-12 |
Substantial Completion | 2025-05-06 | 2025-05-06 |