10344 | Project Development: Concept Development and Preliminary Engineering (Various)
This program will provide funding for Concept Development and Preliminary Engineering work on various identified projects on the state transportation system. Functions to be performed include, but are not limited to, data collection including traffic counts and review of as-built plans, evaluation of existing deficiencies, evaluation of existing safety conditions, environmental screenings, assessment of right-of-way and access impacts, assessment of environmental impacts, identification of a Preliminary Preferred Alternative, National Environmental Protection Agency classification, estimates, technical environmental studies, base mapping/surveying, utility investigations, right of way research and estimates, drainage investigations, geotechnical investigations, engineering in support of the environmental document, an approved environmental document, cost estimates and community outreach/involvement.
Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
---|---|---|---|---|---|---|
Concept Development | STATE | $4.000 | $4.000 | $4.000 | $4.000 | $24.000 |
Program Year Totals: | $4.000 | $4.000 | $4.000 | $4.000 | ||
Total FY24-FY27 Cost: | $16.000 | Total FY24-FY33 Cost: | $40.000 | |||
All costs in millions. |